Last weekend we started our
Kitchen/Laundry renovation. The idea is to do the laundry first, and get
it to a state where we can use it as a mini kitchen while the kitchen
reno is in progress.
So far Denis removed all the cupboards,
pulled off the tiles and wall paper. We then had plumbers move all the
taps down below cupboard height. Next a plasterer popped by to
re-plaster the wall and fill the odd crack.
Right, now we are
at painting stage. Heading to the paint shop tonight to select the
colours... Going for charcoal door, white window and trim, and Dulux
Pale Tendrill Half for the walls.
The flat pack cupboards are
waiting patiently in our garage to be assembled and installed hopefully
this weekend. Yes if all goes to plan we are hoping to finish this
product (except tiling) this weekend...Painting, new power points,
cupboards installed, taps connected, new lighting and shelves etc.
VERY EXCITING. Will post more photos here when complete!